Back to news
IT Support15 November 2026By Timothy, founder of Riverbank IT Systems

Moving Office? The IT Relocation Checklist

Broadband lead times, cabling, phone numbers and the moving-day mistakes that leave firms offline for weeks - a checklist in order of when to act.

Moving Office? The IT Relocation Checklist

The single biggest IT mistake in an office move is treating connectivity like the furniture - something sorted in the last fortnight. Internet circuits take months, not days, and we have watched firms sit in shiny new offices running the whole business off one 4G router for weeks. Here is the checklist in the order things actually need to happen.

Three to six months before: connectivity first

This is the step that cannot be compressed.

  • Check what the new address can actually get. Not the postcode's general coverage - that specific unit. A leased line or full-fibre service available on one side of an industrial estate may not reach your unit.
  • Order early. Standard business broadband over full fibre typically installs in one to three weeks where the service already exists - but a leased line or any circuit needing new construction is routinely quoted at 45 to 90 working days, and sometimes longer where wayleaves or roadworks are involved. Order on day one of the plan, not the last.
  • Check your existing contracts. Notice periods and early-exit fees on the old site's broadband, phones and leased lines. Overlap of a month between the two sites is money well spent, not waste.
  • Decide the comms layout. Where the cabinet goes, how many desk sockets, where Wi-Fi access points sit. Getting a cabling contractor in before the fit-out is finished is far cheaper than surface-mounting everything afterwards.

Six to eight weeks before: the physical layer

  • Book the cabling. Cat6 sockets per desk, plus spares for printers, Wi-Fi points and future desks - double what you think you need is usually right. Floor boxes and desk positions should be agreed with whoever is doing the fit-out, not guessed.
  • Plan Wi-Fi properly. Access point positions decided from the floor plan, not "one in the corner". Open-plan offices, mezzanines and thick stone walls (Edinburgh and Glasgow have plenty) each need a different answer.
  • Sort the phone numbers. If you are on VoIP - and most firms should be - porting numbers to a new provider or reprogramming an existing one takes roughly 10 working days. A geographic number can normally move with you within the same area code; confirm rather than assume.
  • Audit what is actually moving. The office move is the best free inventory you will ever get - every dead laptop and orphaned monitor surfaces. Dispose of old kit securely; it still holds data.

Four weeks before: the dependencies

  • Notify everyone who needs the new address: your IT provider, software vendors with site-licensed products, your alarm and franking suppliers, bank, insurers, clients.
  • Plan the server and comms kit move separately from the desks - it is the last thing off the old site and the first thing live at the new one. If you still run a physical server, this is also the moment to ask honestly whether it should be moving at all or being replaced by cloud. Our server relocation work covers both answers.
  • Back everything up, verified. Not "the backup ran" - a test restore, before anything is unplugged.
  • Book moving-weekend support. Whoever is reconnecting your IT should be on site the day before staff arrive, not booked for the week after.

Moving week: keep the old live until the new works

The resilient pattern: new circuit live and tested before the old one is disconnected, key systems moved and verified over a weekend, and the old broadband left running for a fortnight's overlap. The small overlap cost is nothing against a week of a 20-person office offline.

On the day: internet and Wi-Fi first, then phones, then the server and switches, then desks and printers - tested in that order, because each depends on the last.

After: the fortnight that catches the stragglers

  • Mail redirection is running, the website and Google Business Profile show the new address, email signatures updated.
  • Speed-test the new circuit at each desk area; Wi-Fi coverage checked in the corners and meeting rooms, not just beside the access point.
  • Final disposal of the old site: circuit ceases confirmed in writing, equipment collected, deposits chased.

The costs people forget to budget

The move quote covers desks and boxes; the IT side hides its own extras:

  • Dual-running both sites. A month of overlapping connectivity is deliberate and worth it - but it should be in the budget from the start, not a surprise.
  • Excess construction charges. If the new site needs fibre dug in, the landlord's contribution and the install charge can be material - another reason to survey before signing the lease.
  • Cabling extras. The gap between "a socket per desk" and what is actually needed - comms cabinet, patch panels, Wi-Fi points, power at the cabinet - is where cabling quotes grow.
  • Decommissioning the old site properly. Circuit cease fees, equipment disposal and the final bills have a habit of arriving months later if nobody closes them out in writing.

One last thing nobody puts on a checklist: name an owner for the IT move itself. The moves that hurt are the ones where the removals firm, the fit-out contractor, the landlord and the IT provider each assumed someone else was coordinating. One person - internal or external - holding the whole timeline is worth more than any single item on this list. And on the day itself, keep staff expectations realistic: the first Monday in a new office always has teething issues, so schedule the light week, not the busiest one.

The moves that go smoothly share one habit: the internet was ordered first and everything else planned around its delivery date. If you are planning a Glasgow move, our IT projects team handles relocations regularly, and the free audit can double as a connectivity survey of the new site before you sign the lease - the best time to discover the broadband problem is before you commit.

Discuss your IT priorities

Get a free IT audit from Riverbank IT Systems. Free initial advice, with no obligation to proceed.

Common questions

How far ahead should we order broadband for a new office?

The day you decide to move. Standard full-fibre installs take one to three weeks where service exists, but leased lines and new construction routinely quote 45 to 90 working days - sometimes more with wayleaves. Connectivity is the long-lead item everything else waits on.

Can we keep our phone number when we move?

Usually yes - VoIP numbers move anywhere, and a geographic number can normally move within the same dialling area. Porting takes roughly 10 working days, so start it a month out and confirm with your provider rather than assuming.

Who does the cabling in a new office?

A specialist cabling contractor - ideally before the fit-out finishes, when running cable is cheap and invisible. Plan double the sockets you think you need, plus points for Wi-Fi access points and printers.

Should we move our server or take the chance to replace it?

Ask the question - an office move is the natural moment. If the server is ageing or only survives because nobody wants to touch it, migrating to the cloud or a hosted setup during the move often costs similar effort to relocating the box.

What is the most common mistake in an office IT move?

Ordering internet too late - firms end up running the whole office off a 4G router for weeks. Second place: disconnecting the old site before the new one is proven. A month of overlap between the two is cheap insurance.

What does IT relocation support cost?

It depends mostly on estate size and how much is moving - a small office with cloud services is a job, a server room and 30 desks is more. We scope it in writing after a survey, ideally alongside the free pre-lease connectivity check.